Abstract. Most of the maintenance actions in the construction sector are still reactive and sporadic, based on subjective criteria. Usually, maintenance actions are performed when the building already presents unacceptable degradation levels, and the reactive maintenance actions carried out only correct the anomalies observed, not dealing with the causes, thus leading to additional costs and risks for owners. This study establishes a condition-based maintenance model applied to natural stone claddings. This model has a stochastic nature, in order to deal with the complexity of the degradation phenomena. For that purpose, Petri nets are used, providing an efficient tool to model the deterioration process and the maintenance decisions considered for stone claddings. The maintenance model is a full life-cycle model that encompasses: (i) the stochastic assessment of the degradation condition of the stone claddings, and their expected service life; (ii) and the inspections, maintenance and renewal processes. In this study, three maintenance strategies are considered: (i) major intervention only; (ii) combination of minor and major interventions; and (iii) combination of cleaning operations, minor and major interventions. The impact of the different maintenance strategies in the future performance and remaining service life of stone claddings is analysed, also evaluating the economic impact of each maintenance plan.
Keywords: Degradation, Service Life, Maintenance, Natural Stone Claddings, Petri Net.
The awareness of the building managers and/or owners about the need to maintain their assets more efficiently has increased over the last years (Silva and de Brito, 2019). The maintenance of buildings’ envelope elements is not yet a first concern (Forster and Kayan, 2009; Thomsen and van der Flier, 2011). Usually, maintenance actions are carried out when the buildings’ envelope elements are already severely degraded, or reactive maintenance actions are performed to react to failures and do not deal with the causes (Mobley, 2014), thus leading to additional costs and risks (Dann and Cantell, 2005). Furthermore, regular inspections to assess the condition and maintenance actions on these elements are not mandatory (Shohet et al., 2002). The definition of the end of their service life is subjective, based on the outward appearance, owners/users’ demands and the funds available for maintenance works (Emídio et al., 2014).
Therefore, the development of more efficient methodologies for the implementation of strategic planning of maintenance actions is important (Lacasse and Vanier, 1996; Aikivuori, 1999). The existing tools have several limitations (Ashworth, 1996; Sherwin, 2000; Forster and Kayan, 2009): scarce data about maintenance protocols; poor or non-existent implementation of strategic procedures; lack of information regarding durability and performance of buildings; insufficiently accuracy of the existing maintenance policies; and lack of information about global costs associated with repairs. This information is extremely relevant to managers, insurers, owners or users, and allows the adoption of more sustainable and durable solutions at the design stage and for the definition and implementation of reliable maintenance policies, enabling a more rational management of the building stock.
The main purpose of this study is the development and implementation of a condition-based maintenance model for Natural Stone Claddings (NSC). The proposed model is implemented using a stochastic Petri Nets (PN) framework. The case study selected is composed of 203 NSC, located in Portugal. The sample was established based on the diagnosis of the degradation condition of these claddings in-service performance, through in situ visual inspection. In the methodology developed, three maintenance strategies are assessed: (i) major intervention only; (ii) combination of minor and major interventions; and (iii) combination of cleaning operations, minor and major interventions. The first one represents the most common solution adopted by buildings’ owners. The other two are analysed in order to evaluate the impact of the different alternatives in the claddings’ service life and in the whole-life maintenance costs, for the period under analysis.
Video 1. Spray generated by the 14 ft WAM-V hull at 25 knots. |
PN are a mathematical and graphical modelling tool, introduced by Carl A. Petri in 1962 (Petri, 1962), suitable for description of systems whose dynamics are characterized as being concurrent, asynchronous, distributed, parallel, nondeterministic, and/or stochastic (Murata, 1989).
In a few words, PN can be defined as a bipartite directed graph that comprises two types of nodes, places (representing a state or condition of the system, drawn by circles) and transitions (representing an action, denoted by bars and/or boxes). Both nodes are linked by directed arcs. An arc connects a place with a transition, or vice-versa. Tokens (drawn by small black dots) are stored in places and its distribution (denoted by marking, M) represents the current state of the system. Transitions are responsible for the evolution of the system from one state to another (movement of the tokens between places). A transition is enabled to fire when, in all input places, there is at least one token. Furthermore, it is possible to assign to each transition a firing rate that can be deterministic or modelled by any probabilistic distribution. Figure 1 shows an example of PN composed of three places (p1, p2, p3) and one transition (t1). In this example, the transition is not enabled to fire since place p2 is empty.
The maintenance model, based on the Petri nets methodology, proposed to assess the performance of NSC, is presented in Figure 2. Below, the meaning of each part of the model is briefly described. More information about the model can be seen in Ferreira et al. (2019).
The maintenance model implemented is a condition-based model, where it is assumed that maintenance actions are planned after the condition has been assessed through inspections. In other words, the need for a maintenance action is assessed during inspection, and then, according to the current observed degradation condition of the component under analysis, a decision on intervening is made. The model can be divided in several main parts: (i) degradation process; (ii) inspection process; (iii) maintenance process; (iv) modelling of the maintenance actions; and (v) periodicity of the cleaning operations.
In Figure 2, the degradation process is depicted by five places (p1 to p5) and four timed transitions (t1 to t4). Each place denotes a condition level defined in the classification system adopted, where places p1 and p5 represent, respectively, the best and worst condition level of the classification system. The timed transitions, located between places, model the transition times of moving between different condition levels. The transition times are samples from the appropriate distributions that can be obtained by studying the degradation characteristics of the NSC (Le and Andrews, 2016). The classification system adopted (Table 1), proposed by Silva et al. (2011), is based on visual inspections of the extent of the cladding area affected by the different anomalies. The severity of degradation index, Sw, is defined with the intent of expressing the overall degradation condition of these claddings, and is given by the ratio between the area affected by the defects observed in a NSC, weighted according to their severity, and a reference area equivalent to the total cladding area with the highest possible level of degradation (Equation 1) (Silva et al., 2016).
|
(1) |
where Sw represents the severity of degradation (in %), k the multiplying factor corresponding to the highest degradation condition level of the cladded area A, An the cladding area affected by any defect n (in m2), kn the multiplication factor for the defect n, in terms of their degradation condition, and A the total area of the NSC (in m2). More information about the classification of defects and the determination of Sw can be found in Silva et al. (2016).
Degradation condition | Severity of degradation |
Condition A: No visible degradation | Sw ≤ 1% |
Condition B: Good | 1% < Sw ≤ 8% |
Condition C: Slight degradation | 8% < Sw ≤ 20% |
Condition D: Moderate degradation | 20% < Sw ≤ 45% |
Condition E: Generalized degradation | Sw ≥ 45% |
The inspection process is modelled through the cycle formed by nodes: p6 - t6 - p7 - t5 - p6 (Andrews, 2013). A token in place p6 means that an inspection should not be performed at that time and enables transitions t6 that manages the time intervals between inspections, θ. A token in place p7 means that it is time to perform an inspection, enabling several actions. First, it enables one of the transitions t7 to t11. The firing of one of these transitions allows revealing the true condition of the cladding. A token in places p8, p9, p10, p11 or p12 means, respectively, that the true condition of the cladding is A, B, C, D or E. After that, transition t5 is enabled, which causes the token in place p7 to return to place p6 to wait for the next inspection.
The maintenance process is represented by places p13 to p32 and by the transitions t12 to t40. Here, the available types of interventions are analysed, according to the observed conditions. In the proposed methodology, three intervention levels are considered: cleaning operations, minor and major interventions. This information is introduced in the model through places p13 to p27. Tokens in places p13 to p17 mean cleaning operations must be done, in p18 to p22 that a minor intervention is needed, and in p23 to p27 that a major intervention is required. If there is no token in these places, no interventions are performed. Otherwise, if, for the same condition, there is more than one type of intervention available, the highest impact intervention is performed. A token in places p28, p29, p30 or p31 indicates, respectively, that no intervention, cleaning operations, minor or major interventions are required. After that, the token returns to the degradation process by place p32 and transitions t36 to t40.
In Figure 2, the cleaning operations is modelled by places p33 to p36 and by transitions t41 to t45. The marking of places p33, p34 or p35 means, respectively, that the cleaning operation, when applied, has the effect of improving the condition, supressing the degradation process or reducing the deterioration rate. Then, depending on the impact of the cleaning operation on the cladding, only one transition can be fired. For the minor (places p37 to p40 and transitions t46 to t50) and major (places p41 to p44 and transitions t51 to t55) interventions, the same methodology is implemented.
In this model, the periodicity of the cleaning operations is considered through places p45 to p49 and timed transitions t56 to t60. The introduction of the information that this intervention is available in a given condition level is performed by placing tokens in places p45 to p49. Transitions t56 to t60 are associated with a delay that allows, at the end of θclean time units, the tokens present in places p45 to p49 to be returned to places p13 to p17, allowing cleaning operations to be performed at the next inspection time, if the imposed constrains are complied with.
The case study under examination is composed of 203 NSC directly adhered to the substrate, located in Portugal. The degradation condition of each cladding in the data set was analysed based on in situ visual inspections. The methodology described, was applied to analyse the degradation of NSC over their lifetime. A 150-year time horizon was considered and the cladding is expected to be in perfect conditions at the beginning of the analysis (in condition A).
To find the best distribution that describes the degradation characteristics of the NSC, the degradation process (without maintenance) is applied to the complete sample. Table 2 shows the optimized estimation parameters obtained for the three distribution functions (Exponential, Weibull and Lognormal) analysed, in terms of mean time in each degradation condition and standard deviation, as well as the respective log-likelihood value.
Distributions | Mean [years] | Standard deviation [years] | -log L | ||||||
TA | TB | TC | TD | TA | TB | TC | TD | ||
Exponential | 5.8 | 51.6 | 84.9 | 1.67×107 | 5.8 | 51.6 | 84.9 | 1.67×107 | 161.89 |
Weibull | 4.1 | 42.9 | 22.4 | 49.9 | 7.0 | 10.3 | 1.4 | 2.4 | 125.56 |
Lognormal | 4.2 | 44.0 | 24.3 | 1.54×106 | 11.3 | 13.3 | 0.3 | 2.50×107 | 127.12 |
The parameters of the probability density function are fitted to the historic database based on the concept of maximum likelihood (Kalbfleisch and Lawless, 1985). The likelihood, L, is defined as the predicted probability of occurrence of the observed transitions (Equation 2).
|
(2) |
where pij is the probability of transition from deterioration condition i to j.
The results allow concluding that two-parameter distributions (Weibull and Lognormal) show a better adjustment to the data set than the Exponential distribution. Since Weibull distribution is the one that shows a minor log-likelihood, log L, value and, consequently, a better fit to the historical data, this distribution is chosen to sample the transitions times that specify the movement between different conditions levels.
In this study, three Maintenance Strategies (MS) are considered: (i) major intervention only (MS1); (ii) combination of minor and major interventions (MS2); and (iii) combination of cleaning operations, minor and major interventions (MS3). The different strategies were defined based on previous works and on experts’ judgement. Table 3 presents the fixed costs, application zones and impacts of the different types of interventions considered. It was assumed that an Alpinina marble cladding, directly adhered to the substrate, was used. For example, a cleaning operation of NSC has a cost of 31.37 €/m2, is applied in condition B and improves it to condition A with a probability of 15% or causes no significant improvement with a probability of 85%. Regarding the inspections, a deterministic periodicity of 5 years is considered.
Interventions | Cost [€/m2] | Application zone | Impact of the maintenance actions [%] | ||
PA | PB | Pc | |||
Inspections | 1.03 | All | - | - | - |
Cleaning operations | 31.37 | B | 15.0 | 85.0 | - |
Minor interventions | 68.80 | C | - | 80.4 | 19.6 |
Major interventions | 149.51 | D, E | 100.0 | - | - |
Figure 3 compares the degradation curves obtained for the three MS and for the situation without interventions. The results show that the proposed MS have a significant impact on the mean severity of degradation. For all MS, the mean severity of degradation is less than 8% (condition B), with MS3 showing the greatest variation over time.
Figure 3. Comparison of the degradation curves over time for all maintenance strategies.
On the other hand, if the cumulative costs are analysed (Figure 4), MS2 has the lowest cumulative costs when the discount rate is 0% (Figure 4a) and MS1 for a discount rate of 6% (Figure 4b). For both rates, MS3 is the one with the highest cumulative maintenance costs.
The discount rate is used to balance the initial investment costs against the future maintenance cost. Since this parameter is difficult to predict, two extreme values were considered to assess the sensitivity of the results. Its choice is mainly a political decision, and the value usually ranges between 4% and 6% (van Noortwijk and Frangopol, 2004).
Finally, the number of interventions and the remaining service life for the three MS are analysed (Figure 5). According to Silva et al. (2016), the end of the service life of a NSC varies between 68 and 90 years. The end of the service life occurs when a major intervention is performed. If the first major intervention is analysed (Figure 5a), for MS1, in year 85 there is a probability of 90% of NSC having been replaced at least once. The value agrees with the range suggested by Silva et al. (2016). On the other hand, for MS2, in year 150 there is only a 58% probability that the NSC has been replaced at least once, and, for EM3, this percentage in the same year is reduced to 28%. From this it results that combining major intervention with other intervention works, such as minor interventions and cleaning operations, increases the service life of NSC. Similar observations can be made for the minor intervention (Figure 5b). Considering cleaning operations in MS3 postpones the need of a minor intervention.
Figure 4. Comparison of the cumulative costs over time for all maintenance strategies.
Figure 5. Comparison of the cumulative distribution function of the number of interventions.
In this study, a maintenance model, based on the PN formalism, is proposed to analyse the impact of different MS to control deterioration conditions of NSC. In the proposal methodology, three MS are analysed. These are composed by three different intervention levels: cleaning operations, minor and major interventions. The results reveal that: MS1 presents the lowest cumulative cost for a discount rate of 6%. In MS1, only replacement of the cladding is considered, which does not allow improving the condition over time, as well as its service life. MS3 shows the best degradation results but leads to the highest cumulative costs over the claddings’ lifetime. MS2 seems to be the most rational and adequate solution, according to the model’s assumptions, since it allows increasing the service life and the cumulative costs are competitive when compared with those of MS1. However, in the end, the choice of the best MS is always assumed by the building managers and/or owners and depends on their budgets and target condition for the cladding.
The authors acknowledge the support of the Foundation for Science and Technology, CERIS Research Centre and Instituto Superior Técnico.
Ana Silva: http://orcid.org/0000-0001-6715-474X
Jorge de Brito: http://orcid.org/0000-0001-6766-2736
Luís C. Neves: http://orcid.org/0000-0001-5034-8417
Aikivuori, A.M. (1999). Critical loss of performance - What fails before durability. Performance Based Methods for Service Life Prediction Reports compiled, CIB W80.
Andrews, J. (2013). A modelling approach to railway track asset management. Journal of Rail and Rapid Transit, 227(1), 56-73.
Ashworth, A. (1996). Estimating the life expectancies of building components in life-cycle costing calculations. Structural Survey, 14(2), 4-8.
Dann, N. and Cantell, T. (2005). Maintenance: from philosophy to practice. Journal of Architectural Conservation, 11(1), 42-54.
Emídio, F., de Brito, J., Gaspar, P. L. and Silva, A. (2014). Application of the factor method to the estimation of the service life of natural stone cladding. Construction and Building Materials, 66, 484-493.
Ferreira, C., Neves, L.C., Silva, A. and de Brito, J. (2019). Stochastic maintenance models for ceramic claddings. Structure and Infrastructure Engineering, 16(2), 247-265.
Forster, A.M. and Kayan, B. (2009). Maintenance for historic buildings: a current perspective. Structural Survey, 27(3), 210-229.
Kalbfleisch, J.D. and Lawless, J.F. (1985). The analysis of the panel data under a Markov assumption. Journal of the American Statistical Association, 80(392), 863–871.
Lacasse, M.A. and Vanier, D.J. (1996). A review of service life and durability issues. In Proceedings of the VII International Conference on Durability of Building Materials and Components, Stockholm, Sweden, Vol. 2, 857-866.
Le, B. and Andrews, J. (2016). Petri net modelling of bridge asset management using maintenance-related state conditions. Structure and Infrastructure Engineering, 12(6), 730-751.
Mobley, R.K. (2014). Maintenance Engineering Handbook. New York, NY: MaGraw-Hill Education.
Murata, T. (1989). Petri nets: Properties analysis and applications. Proceedings of the IEEE, 77(4), 541-580.
Petri, C.A. (1962). Kommunikation mit automaten (in German), PhD Thesis, Institut für Instrumentelle Mathematik an der Universität Bonn, Bonn, Germany.
Sherwin, D. (2000). A review of overall models for maintenance management. Journal of Quality in Maintenance Engineering, 6(3), 138-164.
Shohet, I.M., Puterman, M. and Gilboa, E. (2002). Deterioration patterns of building cladding components for maintenance management. Construction Management and Economics, 20(4), 305-314.
Silva, A., de Brito, J. and Gaspar, P.L. (2011). Service life prediction model applied to natural stone wall claddings (directly adhered to the substrate). Construction and Building Materials, 25(9), 3674-3684.
Silva, A., de Brito, J. and Gaspar, P.L. (2016). Methodologies for service life prediction of buildings: With a focus on façade claddings. Switzerland: Springer International Publishing.
Silva, A. and de Brito, J. (2019). Do we need a buildings’ inspection, diagnosis and service life prediction software?. Journal of Building Engineering, 22, 335-348.
Thomsen, A. and van der Flier, K. (2011). Understanding obsolescence: a conceptual model for buildings. Building Research & Information, 39(4), 352-362. doi: 10.1080/09613218.2011.576328
van Noortwijk, J.M. and Frangopol, D.M. (2004). Two probabilistic life-cycle maintenance models for deteriorating civil infrastructures. Probabilistic Engineering Mechanics, 19(4), 345–359.
Published on 01/01/2020
Licence: CC BY-NC-SA license
Are you one of the authors of this document?